An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Move to FNL ECAL/HCAL-Movable Table Setup test beam integration to Fermilab MT6-B3/B4 CALICE technical review

  2. ECAL/HCAL Movable Table Setup no change in basic dimension CALICE technical review

  3. Setup in test beam area update beam area ground dimension ECAL/HCAL Movable Table Control room ? HCAL Movable Table placed in MTB6-B3 ? CALICE technical review

  4. Setup in test beam area inner height ? other equipment ? dump shielding concrete roof support CALICE technical review

  5. Setup in test beam areaone escape route is sufficient ? Escape rote from B4 blocked CALICE technical review

  6. Setup in test beam areacrane height and crane load critical needed hook height over roof 4 m transport weight 15 tons CALICE technical review

  7. Setup in test beam area total height ~ 4 meter CALICE technical review

  8. Setup in test beam areapermanent closed roof (except openings) • installation of Movable Table HCAL and ECAL • with “tricks” only • installation of HCAL modules in position B3 critical • crane needed ! CALICE technical review

  9. Infrastructure at Fermilab(Joe Howell) • Power Conversion • Experiment 2 x 50 Hz 400 VLL 25-32 A • Standard Fermilab 60 HZ, 208v/120v or 480v • Initial checks indicate there is no existing on-site conversion equipment • Continue checking options • Data Transfer • Desire at least 1 Gbit/s Eathernet Link • Erik Ramberg is checking current capacity CALICE technical review

  10. Operations Readiness Clearance(Joe Howell) • Approval given by the Fermilab Partical Physics Division Head indicating that the experiment is safe to operate • Safety Review Committees • Mechanical and Conventional Safety • Electrical • Fire (and flammable gas) • Documentation Review and Equipment Inspection • Help provided to guide through the process CALICE technical review