1 / 5

Introduction

GEO-CAPE Analysis of Mission Implementation Alternatives FY 13 Guidance Letter – Task 8 May 7 , 2013. Introduction. 2012 was a year of great progress for GEO-CAPE Documented NASA state of practice / readiness to use Hosted Payload (HPL) model

Download Presentation

Introduction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GEO-CAPEAnalysis of Mission Implementation AlternativesFY 13 Guidance Letter – Task 8May 7, 2013

  2. Introduction • 2012 was a year of great progress for GEO-CAPE • Documented NASA state of practice / readiness to use Hosted Payload (HPL) model • Completed mission risk analysis and made recommendations for Geo-Pathfinder • HQ accepted recommendation that future GEO-CAPE formulation studies focus only on distributed HPL mission implementation • The Earth Ventures Instrument program selected an instrument (TEMPO) that will do some GEO-CAPE atmospheric science • ESD acknowledged the impact of TEMPO on GEO-CAPE mission planning: “With the award of the Tropospheric Emissions: Monitoring of Pollution (TEMPO) instrument as the first Earth Venture Instrument (EVI-1), a partial change of direction will be needed for the GEO-CAPE activities, as the TEMPO instrument will likely achieve a significant portion of the GEO-CAPE measurement objectives.” • ESD guidance for FY13 GEO-CAPE Task - 8: “Define instrument and measurement risks (and potential mitigation activities), including integration of science products across platforms and technology maturity.” • One of the 2013 GEO-CAPE activities will be a mission implementation study to update the GEO-CAPE atmospheric composition instrument suite in response to ESD guidance

  3. 2013 Instrument and Mission Risks Assessment Overview • The study objectives are to • Assess remaining GEO-CAPE capabilities based on TEMPO requirements and expected performance - The GEO-CAPE atmospheric composition instrument suite (ACIS) = TEMPO + GCIRS • Update GEO-CAPE Atmospheric science capabilities and implementation architecture including schedule requirements • Co-ordinate with TEMPO team and ASWG • Work with SEWG/ESTO on technology needs / recommendations / further work • The study needs to be completed by the end of March and results ready for ESD by early April • The risks were divided into two categories: • Instrument Development • Instrument Operations

  4. Summary of GEO-CAPE Instrument Risks As of7 May2013 5 4 3 2 1 L I K E L I HOOD 1 2 3 4 5 CONSEQUENCES Criticality High Approach M – Mitigate W – Watch A –Accept R– Research L x C Trend Decreasing (Improving) Increasing (Worsening) Unchanged Med Low

  5. Summary of GEO-CAPE Operational Risks As of7 May2013 5 4 3 2 1 L I K E L I HOOD 1 2 3 4 5 CONSEQUENCES Criticality High Approach M – Mitigate W – Watch A –Accept R– Research L x C Trend Decreasing (Improving) Increasing (Worsening) Unchanged Med Low

More Related