An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Operation ManagementMPS &MRP Rachmat A. Anggara PMBS, BOPR 5301, Session 6

  2. OUTLINE • MRP & MPS Structure • MRP Management • MRP Dynamics • MRP and JIT • Lot-Sizing Techniques

  3. OBJECTIVES • Understand Bill of Materials • Master Production Schedule • Materials Requirement Planning • Lot sizing

  4. DEMAND TYPE • Independent • Dependent • The demand for one item is related to the demand for another item • Given a quantity for the end item, the demand for all parts and components can be calculated

  5. DEPENDENT DEMAND Effective use of dependent demand inventory models requires the following • Master production schedule • Specifications or bill of material • Inventory availability • Purchase orders outstanding • Lead times

  6. DEPENDENT DEMAND Effective use of dependent demand inventory models requires the following • Master production schedule • Specifications or bill of material • Inventory availability • Purchase orders outstanding • Lead times

  7. Production Capacity Inventory Marketing Customer demand Finance Cash flow Procurement Supplier performance Human resources Manpower planning Management Return on investment Capital Engineering Design completion Aggregate production plan Change production plan? Master production schedule OPERATION MANAGEMENT FLOW Materials Requirement Planning

  8. MASTER PRODUCTION SCHEDULE Master Production Schedule gives production, planning, purchasing, and top management the information needed to plan and control the manufacturing operation. The application ties overall business planning and forecasting to detail operations through the Master Production Schedule (inventory& logistics solutions) MPS -Forecasts -Aggregate Planning -Customer order -Capacity -What to produce -When To Produce -How Much to Produce

  9. MASTER PRODUCTION SCHEDULE MPS is disaggregation of Aggregate Planning

  10. MPS STRUCTURE

  11. BILL OF MATERIALS • List of components, ingredients, and materials needed to make product • Provides product structure • Items above given level are called parents • Items below given level are called children

  12. BILL OF MATERIALS

  13. LEAD TIMES • The time required to purchase, produce, or assemble an item • For purchased items – the time between the recognition of a need and the availability of the item for production • For production – the sum of the order, wait, move, setup, store, and run times

  14. Must have D and E completed here so production can begin on B Start production of D 1 week 2 weeks to produce D B 2 weeks E A 2 weeks 1 week E 1 week 2 weeks G C 3 weeks F 1 week D | | | | | | | | 1 2 3 4 5 6 7 8 Time in weeks TIME PHASING FOR PRODUCT STRUCTURE

  15. Data Files Output Reports MRP by period report BOM Master production schedule MRP by date report Lead times (Item master file) Planned order report Inventory data Purchase advice Material requirement planning programs (computer and software) Exception reports Order early or late or not needed Order quantity too small or too large Purchasing data MATERIAL REQUIREMENT PLANNING Figure 14.5

  16. MRP STRUCTURE • INPUTS • Objective: find material plans [planned order releases] for all parts • Data requirements MPS BOMs Inventory records file • Gross requirements are ultimately derived from MPS • But in calculations, the gross requirements for a part depend only on the planned order releases of the parent parts

  17. MRP STRUCTURE (2) • Parameters • Gross requirements  demand for part (forecast) • Schedule receipts planned completion times for batches of parts which have been already ordered • Projected on hand Number of ready stock • Net requirements  Number of required item on that period • Planned-order receipts planned completion times for batches of parts which have not yet been ordered • Planned-order releases planned start times for batches of parts which have not yet been ordered

  18. MRP STRUCTURE (3) • OUTPUTS • Planned orders - schedule indicating the amount and timing of future orders. • Order releases - Authorization for the execution of planned orders. • Changes - revisions of due dates or order quantities, or cancellations of orders.

  19. MRP STRUCTURE (3) • OUTPUTS • Planned orders - schedule indicating the amount and timing of future orders. • Order releases - Authorization for the execution of planned orders. • Changes - revisions of due dates or order quantities, or cancellations of orders.

  20. MRP’s TEMPLATE

  21. allocations gross requirements + total requirements scheduled receipts on hand – + = net requirements available inventory MRP’s TEMPLATE The logic of net requirements

  22. MRP’s TEMPLATE example A LT 2 B (2) LT 2

  23. MRP’s TEMPLATE example MRP for item B??

  24. MRP’s TEMPLATE example MRP for item B??

  25. LOT SIZING TECHNIQUE • Lot-for-lot techniques order just what is required for production based on net requirements • May not always be feasible • If setup costs are high, costs may be high as well • Economic order quantity (EOQ) • EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand • Part Period Balancing (PPB) looks at future orders to determine most economic lot size

  26. LOT SIZING TECHNIQUE LOT FOR LOT No on-hand inventory is carried through the system Total holding cost = $0 There are seven setups for this item in this plan Total setup cost = 7 x $100 = $700 Holding cost = $1/week; Setup cost = $100

  27. LOT SIZING TECHNIQUE EOQ Holding cost = $1/week; Setup cost = $100; Average weekly gross requirements = 27; EOQ = 73 units

  28. LOT SIZING TECHNIQUE PART PERIOD BALANCING Find Economic Part Period Holding cost = $1/week; Setup cost = $100; EPP =Setup cost/holding cost= 100 units 2. Combine each period until reach/closest to EPP (period 1, period 1-2, period 1-3, period 1-4. and so on… 3. Stop until combined period larger than EPP

  29. LOT SIZING TECHNIQUE PART PERIOD BALANCING Holding cost = $1/week; Setup cost = $100; EPP = 100 units

  30. 10 55 LOT SIZING TECHNIQUE PART PERIOD BALANCING 2 30 2, 3 70 2, 3, 4 70 2, 3, 4, 5 80 2, 3, 4, 5, 6 120 Combine periods 2 - 5 as this results in the Part Period closest to the EPP Combine periods 6 - 9 as this results in the Part Period closest to the EPP 6 40 6, 7 70 6, 7, 8 70 6, 7, 8, 9 100

  31. LOT SIZING TECHNIQUE PART PERIOD BALANCING Fulfill The MRP TEMPLATE PLEASE

  32. DISTRIBUTION RESOURCE PLANNING Using dependent demand techniques through the supply chain • Gross requirements, which are the same as expected demand or sales forecasts • Minimum levels of inventory to meet customer service levels • Accurate lead times • Definition of the distribution structure

  33. DISTRIBUTION RESOURCE PLANNING

  34. ENTERPRISE RESOURCE PLANNING • An extension of the MRP system to tie in customers and suppliers • Allows automation and integration of many business processes • Shares common data bases and business practices • Produces information in real time • Coordinates business from supplier evaluation to customer invoicing

  35. ENTERPRISE RESOURCE PLANNING • ERP systems have the potential to • Reduce transaction costs • Increase the speed and accuracy of information • Facilitates a strategic emphasis on JIT systems and integration

  36. ENTERPRISE RESOURCE PLANNING

  37. HOME WORK!!!