HBD Commissioning

HBD Commissioning. Progress from October 3 to November 28, 2006. Itzhak Tserruya DC meeting, BNL December 13, 2006. Done or almost done. in progress. to be done. Pre-beam commissioning (I). Present status: the two detectors installed

bnaquin
Download Presentation

HBD Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD Commissioning Progress from October 3 to November 28, 2006 Itzhak Tserruya DC meeting, BNL December 13, 2006

  2. Done or almost done • in progress • to be done Pre-beam commissioning (I) • Present status: • the two detectors installed • all cables (signal, HV and LV) tested, installed and connected • CF4 gas recirculation system operational but still on commissioning phase • UV lamp for CsI QE monitoring installed and operational, procedure being optimized • Heating and cooling systems almost ready (waiting for blowers) • CF4 gas monitoring system – expected to be installed this week

  3. Both detectors installed HBD East (back side) Installed 10/19/06 HBD West (front side) Installed 9/4/06

  4. Water inside HBD Room temperature ≈ 20 deg. Flow: Ar 3l/min

  5. Relative CsI QE monitoring • October 17, 18: East measured at SUNY with Ar • December 4: East and West measured at BNL with Ar • December 8: East and West measured at BNL with CF4 • Finding: • - East @BNL = East @ SUNY • East very similar to West • Values in CF4 ≈ 2 x Values in Ar • Very encouraging. A new set of measurements under better and more reproducible conditions is planned to serve for long term reference

  6. Done or almost done • in progress • to be done Pre-beam commissioning (II) • HV system: • All six HV PS units tested • 500 V on each module • operational voltage on each module: The LeCroy HV PS does not offer enough protection. We are developing and testing a safe procedure to go to operating voltage. Powering scheme: 2 HV PS one for the mesh and one for the triple GEM stack through a 3 branch resistive chain. (across the GEMs there is only one resistor R2 and not two as in this diagram).

  7. Done or almost done • in progress • to be done Pre-beam commissioning (III) • Detector readout: • Readout electronics delivered, operational and ready to take data in stand-alone mode. • noise optimization • dead channel count • pedestal runs done routinely • timing and data taking with pulser done routinely • ADC charge calibration for all detector modules • first order zero suppression -- Chi

  8. Examples of raw data 12x16 ns sample TDC signal S(8+9+10)/3 – S(0)

  9. Mean - West Black: double peaks Blue: large pads at detector edge

  10. Mean - East Black: double peaks Blue: large pads at detector edge

  11. Sigma - West Black: double peaks Blue: large pads at detector edge

  12. Sigma - East Black: double peaks Blue: large pads at detector edge

  13. Summary • Noise level is excellent:  ~ 2 ADC counts  3 ~ 6 ADC counts 0.6 fC  0.37 e at a gain of 104 • Channels without signal: 28 in total  solved • Channels with double peaks: 18 in total • Channels with low signal: 4 in total Remaining problems in less than 1% of all channels! (Origin under study. Suspicion that double peaks are due to saturated pulses.)

  14. Done or almost done • in progress • to be done Pre-beam commissioning (IV) • Monte Carlo simulations • basic geometry and materials in • reconstruction up to the pad response • 3d field map in +- configuration • look up table • cluster reconstruction and cluster splitting • tracking central arm to HBD

  15. HBD in PISA Hits per sector X-Y hits Z-Y Hits

  16. Number of detected Cherenkov photons per electron

  17. Event Display - Clusters

  18. Pre-beam commissioning (V) • HBD online monitoring: • Event display: pad response • Event display: cluster response • Pulse height distribution of a detector module • Pad frequency vs. pad number • Cluster size distribution • Cluster pulse height distribution HBD trigger • First discussions started Very good progress over the last two months (in spite of QM) and we still have about 6 weeks to complete this program before we see collisions. I think this is doable.