HBD HV Commissioning

HBD HV Commissioning. Itzhak Tserruya, HBD meeting, February 27, 2006. Last week highlights. Completion of the module by module conditioning. 2 nd round of Bertan tests on 54 GEMs.

jordanr
Download Presentation

HBD HV Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD HV Commissioning Itzhak Tserruya, HBD meeting, February 27, 2006

  2. Last week highlights • Completion of the module by module conditioning. • 2nd round of Bertan tests on 54 GEMs. • Resistor changes on the entire detector completed. In the majority of cases the changes produced the anticipated change of bringing dI close to zero. The few cases where the change did not work are fullly understood. • A group of seven modules from the upper part of the detector (EN3, EN4, EN5, ES3, WN3, WN5, WS5) were brought together to 3600V: • West: 1 massive trip in 7h • East: 5 massive trips in 7h (some of them could have been triggered by ES5 that draws negative current).

  3. 2nd round of Bertan test • Performed on 54 GEMs (53 successful, 1 inconclusive). • Comparison of 1st and 2nd round: Total T M B • no change 30 5 12 13 • improvement 2 2 • deterioration* 11 8 2 1 • new problem 10 5 2 3 * Deteriaration generally means that a non-ohmic behavior became more non-ohmic getting closer to a dead short.

  4. Single & group conditioning • The 7 modules (EN3, EN4, EN5, ES3, WN3, WN5, WS5) were selected because they were stable over the last days and with dI close to zero. • Summary of single module conditioning: trips during ramping up trips at 3600 V ------------------------------------------------------------------------- EN3 0 0/4.8h EN4 Failed (13 trips/2h at 3400/3550) This module was drawing dI = -0.9% EN5 0 1/4.8 ES3 0 0/6.5h -------------------------------------------------------------------------------- Group 2 3/7h* -------------------------------------------------------------------------------- WN3 1 0/4h WN5 0 0/4h WS5 2 0/8h ------------------------------------------------------------------ Group 0 1/7h * 2 could have been triggered by ES3 that was by mistake added to the group for about 3h. Conclusions: • EN4 should be conditioned again separately. • We should require each module to be stable at 3600V before adding it to the group.

  5. Comments and recommendations • Resisitors should be changed if: • Bertan test and HV_Gui give a consistent picture AND • the module showed stability over at least one week bracketing the Bertan test. • The vast majority of trips is harmless. Only a very small fraction produces some damage that is evidenced by a sudden jump in dI right after a trip. • We should find a quick way to alert us when a sudden change in current occurs.

  6. Comments & Recommendations • Many of the damaging trips have occurred on Feb. 6-8 when magnet operations took place. Coincidence or real effect? • For the time being, whenever magnet operations take place I recommend to ramp down to zero the entire detector. After completion of magnet operation, we should restore HV very cautiously. Modules may require reconditioning after changes in magnetic field configuration. I recommend to restore HV module by module the first time.

  7. What’s next? • Select a group of good modules from the lower part of the detector and follow the same procedure as for the group of 7 from the upper part of the detector, i.e.: • One by one ramp the up to 3600 V, stay 1 h at 3600V and then back to 3200V • Ramp the entire group to 3600 V and stay there at least 6h. • Take the two groups together to 3600 V • Work/watch the other modules. • Since RHIC is delayed by two weeks we should do one operation at a time to allow unambiguous diagnostics.