Jonathon Gridley Senior Thesis – Spring 2007 Mechanical Option

South Jefferson High School. Energy Efficient Mechanical System Alternatives. S OUTH J EFFERSON H IGH S CHOOL. Jonathon Gridley Senior Thesis – Spring 2007 Mechanical Option. PRESENTATION OUTLINE. BUILDING BACKGROUND EXISTING SYSTEMS DESIGN OBJECTIVES MECHANICAL SYSTEM REDESIGNS

cleary
Download Presentation

Jonathon Gridley Senior Thesis – Spring 2007 Mechanical Option

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. South Jefferson High School Energy Efficient Mechanical System Alternatives SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley Senior Thesis – Spring 2007 Mechanical Option

  2. PRESENTATION OUTLINE • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option

  3. PRESENTATION OUTLINE BUILDING BACKGROUND • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS Location and Site: Charles Town, WV 25414 Occupancy : 1200 students Size: 199,717 sq.ft. Number of Stories: 2 stories Total Building Cost:$34 Million Dates of Construction:February 2006 – August 2007 Project Delivery Method:Design-Bid-Build SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  4. PRESENTATION OUTLINE BUILDING BACKGROUND • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • BUILDING LAYOUT AND USES: • Academic Wings and Administration Area • Learning Resource Center and Science and Technology • Dining • Kitchen/Servery • Physical Education • Creative Arts • Library SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Building Zone Designations Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  5. PRESENTATION OUTLINE EXISTING SYSTEMS • MECHANICAL SYSTEM: • AIR SIDE • 14 Packaged Roof Top Units ranging from 6,000 to 25,500 CFM • (6) VAV System with Fan Powered Boxes and VFD • (8) Constant Volume Air Handlers • WATER SIDE • Two 4,717 MBH Electric Boilers • Primary-Secondary Variable Volume Pumping • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Heating Plant Schematic Air Side Schematic Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  6. PRESENTATION OUTLINE DESIGN OBJECTIVES • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS Green Design Initiative: • Reduce energy consumption and emission • Low Operating and Maintenance Costs SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL • Short life cycle payback • Improve indoor air quality • Alternative Mechanical Systems: • VAV System with Chilled Water Plant • Ground Source Heat Pump System Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  7. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: VAV System with Chilled Water Plant • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • Advantages: • Lower Noise Levels • Local Control of Temperature • Better Dehumidification • Longest Service Life • Good Energy Conservation • Energy Reclaim SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL • Disadvantages: • Higher First Cost • Filter Maintenance • Requires More Space Above Ceiling • Air Cooled Chiller On-Site VAV with Chilled Water Plant Diagram Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  8. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: VAV System with Chilled Water Plant • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • Two 300 ton air-cooled chillers replace DX condensing units • 4-pipe system adds chilled water piping to building • External site for plant by kitchen loading docks surrounded by screen wall to reduce noise • Enthalpy Wheels added to Roof Top Units SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL York Air-Cooled Screw Chiller Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  9. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: Ground Source Heat Pump • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • Advantages: • “Green” Concept • No Cooling Tower or Chiller • Good Dehumidification • Low Maintenance Cost • Better Indoor Air Quality • Longer Life SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL • Disadvantages: • Higher First Cost • On-Site Area Required to Bury Piping • Dependant on the Quality of Electricity Ground Source Heat Pump Diagram Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  10. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: Ground Source Heat Pump • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • Independent 2-Pipe Ground Source Heat Pump System • High Efficiency Heat Pumps • 240 Boreholes, 475 ft deep, located under the future football and soccer practice fields • Dedicated Outdoor Air Units replace multiple space RTU’s SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL American Standard Inc. Packaged DOAS Florida Ground Source Heat Pumps Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  11. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: Air-to-Air Heat Recovery and Humidity Control • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • ENTHALPY WHEELS: • Transfer heat and moisture between EA and OA stream • Incorporated in RTU’s and DOAS units • HUMIDITY CONTROL: • Densely Populated Spaces – Require Humidity Control • Maintain RH Levels Between 30% and 50% SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Enthalpy Wheel Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  12. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: Energy and Cost Analysis • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL VAV with CWP: Saves 6% in total building energy consumption GSHP: Saves 25% of total building energy Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  13. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: Energy and Cost Analysis • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS VAV with CWP: Cost More in 1st Cost and Maintenance Cost GSHP: Saves $38,278 in Life Cycle Cost SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL VAV with CWP: Does Not Payback in 20 years GSHP: Pays back in 18.7 years. Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  14. PRESENTATION OUTLINE MECHANICAL SYSTEM REDESIGNS: Emissions • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS Emission Reduction: SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL VAV with CWP: Reduces Emissions 7% GSHP: Reduces Emissions 30% Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  15. BREADTH TOPICS: Lighting PRESENTATION OUTLINE • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • Replace existing fixtures in Classrooms and Corridors with High Efficiency fixture, lamp, and ballast combination • Maintain proper task lighting • Reduced lighting fixture power density from: • 1.07 to 0.97 W/S.F. • Saves $133,000 Annual SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  16. BREADTH TOPICS: Construction Management PRESENTATION OUTLINE • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  17. BREADTH TOPICS: Construction Management PRESENTATION OUTLINE • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  18. PRESENTATION OUTLINE CONCLUSIONS AND RECOMMENDATIONS • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL 5 = Excellent 4 = Above Average 3 = Below Average 2 = Below Average1 = Poor Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  19. PRESENTATION OUTLINE ACKNOWLEDGEMENTS • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS MECHANICAL PROFESSORS: Dr. Bahnfleth, Dr. Friehaut, J.J., Dr. Mumma, and Dr. Srebric PROFESSIONALS: Ryan Buff, John Weiland, Damion Spahr, and Paul Patrelli FRIENDS AND FAMILY: Parents, Dave, Rod, Kevin, Justin, Eric, Krista, Amy SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  20. PRESENTATION OUTLINE Questions • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  21. PRESENTATION OUTLINE Energy and Cost Analysis; • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  22. PRESENTATION OUTLINE Electric Demand Cost (Equip.) • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  23. PRESENTATION OUTLINE Electric Energy Cost (Equip.) • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  24. PRESENTATION OUTLINE Cooling Energy Consumption (Equip) • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  25. PRESENTATION OUTLINE Loop Design Thermal Conductivity • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS • Thermal conductivity is generally dependent on density, moisture content, mineral content • Soils: • Clays (15% moisture) 0.4 - 1.1 Btu/hr-ft-F • Clays (5% moisture) 0.3 - 0.8 • Sands (15% moisture) 0.6 - 2.2 • Sands (5% moisture) 0.5 – 1.9 • Rocks: • Granite 1.3 – 2.1 Btu/hr-ft-F • Basalt 1.2 – 1.4 • Limestone 1.4 – 2.2 • Sandstone 1.2 – 2.0 • Shale 0.8 – 1.4 • Grouts: • Standard Bentonite 0.42 • Thermally-enhanced 0.85 – 1.40 SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  26. PRESENTATION OUTLINE Electricity • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS Electricity Cost: Demand Charge First 3,000 kVA …………………………………… $7.923 per kVA Next 14,000 kVA ………………………………… $7.456 per kVA Additional kVA …………………………………… $7.104 per kVA Energy Charge All kW …………………………………………… $0.02198 per kW SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  27. PRESENTATION OUTLINE Maintenance • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  28. PRESENTATION OUTLINE Wellfield • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  29. PRESENTATION OUTLINE GSHP Cost • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007

  30. PRESENTATION OUTLINE Screw Chiller • BUILDING BACKGROUND • EXISTING SYSTEMS • DESIGN OBJECTIVES • MECHANICAL SYSTEM REDESIGNS • VAV System with Chilled Water Plant • Ground Source Heat Pump • Air-to-Air Heat Recovery and Humidity Control • Energy and Cost Analysis • Emissions • BREADTH TOPICS • Lighting • Construction Management • CONCLUSIONS AND RECOMMENDATIONS • ACKNOWLEDGEMENTS • QUESTIONS SOUTH JEFFERSON HIGH SCHOOL SOUTH JEFFERSON HIGH SCHOOL Jonathon Gridley-Mechanical Option Architectural Engineering Senior Thesis – Spring 2007