Options for the outbound logistics with time & cost. Shipment Flow Mode A ( TPK- BLP- SZ by truck ). Time Frame( Total 1 working days). Release by Customs & Move by truck. Arrange import + export clearance. Bonded Logistics Park. Arrival HUB. Arrival SZ. Move to BLP. Day 1
E N D
Options for the outbound logistics with time & cost Shipment Flow Mode A ( TPK- BLP- SZ by truck) Time Frame( Total 1 working days) Release by Customs & Move by truck Arrange import + export clearance Bonded Logistics Park Arrival HUB Arrival SZ Move to BLP Day 1 AM 09:00 ~ PM 16:00 Day1 need to be arrived before AM 9:00 Day1 AM 9:00 Day 1 of PM 17:00 Departure on PM 18:00 Day 2 AM 4:00 ~ 6:00 Trucking time 10 hours ( ETA Day 2 AM 3:00)
Options for the outbound logistics with time & cost Time Frame( Total 2 working days) Shipment Flow Mode B ( TPK- BLP- SZ by air) Release by customs and move to airport Arrange import+ export clearance Bonded Logistics Park Arrival HUB Move to BLP Fly to SZ Day 1 of 17:00 Truck to airport Day 1 AM 09:00 ~ PM 16:00 Day 2 AM 09:00 flight and arrives SZ airport for unloading at 10:00 Day 2 AM 12:00 arrives Day1 need to be arrived before AM 09:00
Options for the outbound logistics with time & cost Shipment Flow Mode C ( TPK- HK- SZ by air) Time Frame( Total 2 working days) Clearance Done and Loading to Truck move To SZ Arrange import+ re-export clearance Arrives HK and unloading Fly to HK By KA Airline Arrival SZ Customs clearance Clearance Customs In SZ Move to XM Airport Arrival HUB Day 2 AM 9:00 ~ PM 16:00 Trucking time 4 hours arrival 21:00 Day 2 PM 24:00 Day 1 ETD XM PM 20:55 Day 2 PM 17:00 Day 2 PM 22:00 Day1 arrives HK PM 21:35 Day1 PM 16:00 Day1 AM 9:00 ~ 12:00
Options for the outbound logistics with time & cost Shipment Flow Mode D ( TPK - HK – SZ by truck) Time Frame( Total 3 working days) Clearance Done and Loading to Truck move To SZ Export Transfer And Re-ship To HK Arrange import+ re-export clearance Loading to Bonded truck to SZ Arrives HK and unloading Customs clearance Arrival SZ Clearance Customs In SZ Arrival HUB Trucking time 4 hours arrival 16:00 Day 3 AM 9:00 Day 2 AM 04:00 arrival SZ and re-ship to HK PM13:00 Day 3 PM 19:00 Day 3 PM 12:00 Day 3 PM 17:00 Day1 PM 18:00 Day1 AM 9:00 to 16:00 PM Day2 arrives HK PM 17:00
Process flow for Inbound LCM Mode from XM BLP : By Air (Around 1 working day) Release by Customs & Move by truck Arrange import + export clearance Bonded Logistics Park Arrival TPK Arrival SZ Move to BLP Day 1 AM 09:00 ~ PM 16:00 Day1 need to be arrived before AM 9:00 Day1 AM 9:00 Day 1 of PM 17:00 Departure on PM 18:00 Day 2 AM 4:00 ~ 6:00 Trucking time 10 hours ( ETA Day 2 AM 3:00) XM BLP 1 day not including cargo inspection on spot
Process flow for Inbound LCM Mode from XM BLP : By Air (Around 1 working day) Release by Customs & Move by truck Arrange import + export clearance Bonded Logistics Park Arrival TPK Arrival SZ Move to BLP Day 1 AM 09:00 ~ PM 16:00 Day1 need to be arrived before AM 9:00 Day1 AM 9:00 Day 1 of PM 17:00 Departure on PM 18:00 Day 2 AM 4:00 ~ 6:00 Trucking time 10 hours ( ETA Day 2 AM 3:00) XM BLP 1 day not including cargo inspection on spot
Process flow for Inbound LCM Mode from HK to Xiamen - Air TPK Clear customs 0.5 day HK 1day Supplier Clear customs 0.5day Arrival TPK 1. Received goods • Arrival HK • Transfer to XM 1. Export customs clearance 2. Arrange shipment to HK • Arrival in XM • Import customs clearance • Ship to TPK factory TPK customs declaration 0.5 day not including cargo inspection on spot
Process flow for Inbound LCM Mode from XM BLP : By Air (Around 1 working day) Release by Customs & Move by truck Arrange import + export clearance Bonded Logistics Park Arrival TPK Arrival SZ Move to BLP Day 1 AM 09:00 ~ PM 16:00 Day1 need to be arrived before AM 9:00 Day1 AM 9:00 Day 1 of PM 17:00 Departure on PM 18:00 Day 2 AM 4:00 ~ 6:00 Trucking time 10 hours ( ETA Day 2 AM 3:00) XM BLP 1 day not including cargo inspection on spot
Process flow for Inbound LCM Mode from XM BLP : By Air (Around 1 working day) Release by Customs & Move by truck Arrange import + export clearance Bonded Logistics Park Arrival TPK Arrival SZ Move to BLP Day 1 AM 09:00 ~ PM 16:00 Day1 need to be arrived before AM 9:00 Day1 AM 9:00 Day 1 of PM 17:00 Departure on PM 18:00 Day 2 AM 4:00 ~ 6:00 Trucking time 10 hours ( ETA Day 2 AM 3:00) XM BLP 1 day not including cargo inspection on spot